Two more days to D-Day! Update of what happened earlier:
01. To vanish the parquet floor
- Left with the Main Entrance
02. To install Franke Island Hood
- Left with Kitchen area
04. To commission electrical outlets
- Left with Kitchen area
05. To measure boxing up of lights and to order the Acrylic light shades
- Delivery on Saturday
06. To fix Guest Toilet granite top
07. To fix Guest Toilet vanity wardrobe
08. To fix Guest Toilet lock
09. To measure for kitchen solid top
11. To final coat timber stain for balcony
12. To touch up [paint] - interior and exterior
- Left with Living Room, Kitchen and Guest Toilet
13. To fill up holes at false ceiling and paint
- Left with Kitchen area
14. To fix taps and mixers at kitchen, master and guest toilets
15. To install lock at main gate
16. To fix curtain rods and curtains
17. To fix glass at Master Toilet
18. To fix glass at Guest Toilet
19. To fix mirror at Master Toilet
20. To de-wax and polish floor tiles
21. To clean windows
22. To fix kitchen back splash [wet and dry areas]
23. To commission Daikin Air-con
24. To install doors for kitchen top hung cabinets
25. To install doors for kitchen tall cabinets
26. To rectify [re-laminate] Master bedroom door
27. To 'iron' laminate at Main Door
28. To clear all debris
29. To re-laminate Guest Room door
Pictures Update:
The 'Sensitive' Hole Issue - Living Room TV Console:
And Mr Franke is finally installed!!:
It will be a LLLOOONNNGGGGG day tomorrow. We are trying to accomplish 80% of those works still outstanding.